Scheduled Service Change: Wipe and reconfigure sfr1-qfx / sfr2-qfx (Rhodes Hall server farm) switches
Event:
2024-06-10 04:00:00
Expected Duration:
2024-06-10 07:00:00
Status:
Closed
Brief Description:
Update: On June 10, from 4-7am, appliances connected to the sfr1-qfx and sfr2-qfx switches will lose network connectivity for several minutes while the two switches are re-imaged, reconfigured and upgraded. See description for full list.
User Impact:
All network connections through these switches and the ones downstream from them will be lost for the duration of the maintenance.
Services Affected:
Network
Subsites Affected:
Managed Servers
Wired Network
Full Description:
Update: The outage will begin at 4am. On June 10, from 4-7am, the following appliances connected to the sfr1-qfx and sfr2-qfx switches will lose network connectivity for several minutes while the two switches are re-imaged, reconfigured and upgraded:
- xe-0/0/0 up up sfr1-2540:25:Trk1
- xe-0/0/1 up up sfr2-2540:25:Trk1
- xe-0/0/2 up up HPC01:Bay1:X1
- xe-0/0/3 up up HPC01:Bay2:X1
- xe-0/0/4 up down HPC02:Bay1:X5
- xe-0/0/5 up down HPC02:Bay2:X5
- xe-0/0/6 up up g10-sandbox:pci1-1
- xe-0/0/7 up up styx04_pci0-1
- xe-0/0/8 up up styx05_pci0-1
- xe-0/0/9 up up styx06_pci0-1
- xe-0/0/10 up up HPC08:Bay1:X5
- xe-0/0/11 up up HPC08:Bay2:X5
- xe-0/0/12 up up HPC10:Bay1:X5
- xe-0/0/13 up up HPC10:Bay2:X5
- xe-0/0/14 up up HPC12:Bay1:X5
- xe-0/0/15 up up HPC12:Bay2:X5
- xe-0/0/16 up up styx01_pci0-1
- xe-0/0/17 up up styx02_pci0-1
- xe-0/0/18 up up styx03_pci0-1
- xe-0/0/19 up up swaziland04:pci4-1
- xe-0/0/22 up up rhodes-nas07:A:E1A
- xe-0/0/23 up up rhodes-nas07:B:E1A
- xe-0/0/24 up up styx07_pci0-1
- xe-0/0/25 up up styx08_pci0-1
- xe-0/0/26 up up styx09_pci0-1
- xe-0/0/28 up up styx10_pci0-1
- xe-0/0/29 up up styx11_pci0-1
- xe-0/0/30 up up rhodes-nas09:A
- xe-0/0/31 up up rhodes-nas09:B
- ge-0/0/36 up up charger:s0p1
- ge-0/0/37 up up coralbells4:eth0
- ge-0/0/38 up up larkspur6:eth0
- ge-0/0/39 up up echinacea4:eth0
- ge-0/0/41 up up corabells3:eth0
- ge-0/0/42 up up larkspur5:eth0
- ge-0/0/43 up up echinacea3:eth0
- xe-0/0/45 up up bigip2-4600:11.0
several iLo connections on sfr1-2540 and sfr2-2540
Note: the bigIP appliance in CCC will not be impacted during this maintenance.
CIT TDX ID:
1350578
Timeline of Changes
Description | Current Status | Date | Time |
---|---|---|---|
Update: The outage will begin at 4am. On June 10, from 4-7am, the following appliances connected to the sfr1-qfx and sfr2-qfx switches will lose network connectivity for several minutes while the two switches are re-imaged, reconfigured and upgraded:
several iLo connections on sfr1-2540 and sfr2-2540 Note: the bigIP appliance in CCC will not be impacted during this maintenance. |
2024-06-06 | 12:24:06 | |
Reminder: On June 10, from 5-7am, the following appliances connected to the sfr1-qfx and sfr2-qfx switches will lose network connectivity for several minutes while the two switches are re-imaged, reconfigured and upgraded:
several iLo connections on sfr1-2540 and sfr2-2540 Note: the bigIP appliance in CCC will not be impacted during this maintenance. |
2024-06-06 | 11:00:51 | |
The following appliances connected to the sfr1-qfx and sfr2-qfx switches will lose network connectivity for several minutes while the two switches are re-imaged, reconfigured and upgraded:
several iLo connections on sfr1-2540 and sfr2-2540 Note: the bigIP appliance in CCC will not be impacted during this maintenance. |
2024-05-31 | 08:37:10 |