Skip to main content

Performance Issue: CIT Server Farm firewall upgrade issuesw

Last Updated:
2019-06-23 16:39:27
Event:
2019-06-23 13:24:00
Status:
Closed
Brief Description:
Datacenter networks being impacted by Server Farm firewall upgrade issues
User Impact:
Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers. ClearPass and Eduroam may experience issues, Rover should be ok.
Workaround:
There is no workaround for this issue
Current Status:
The Data Center has been stable since Noon. Managed firewall upgrades for Datacenter complete.
Services Affected:
Managed Firewall
Data Center Service
Full Description:
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues.
Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers.



Timeline of Changes

Description Current Status Date Time
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues. Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers. The Data Center has been stable since Noon. Managed firewall upgrades for Datacenter complete. 2019-06-23 16:39:27
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues. Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers. The maintenance is running bit past the scheduled window. We expect to be completed by 12:30. The Serverfarm is stable at this time. 2019-06-23 16:05:52
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues. Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers. We are still experiencing network issues in the CIT server farm and Uris Managed Firewall environments. CIT staff working to resolve. 2019-06-23 15:28:01
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues. Impacting CIT Data Center server access including Cornell.edu, AD and other central services..managed servers. CIT Staff working to correct resolve issue and complete the firewall upgrade. 2019-06-23 14:05:03
Scheduled CIT Server Farm firewall upgrade in progress and we are running into issues. CIT Staff working to correct resolve issue and complete the firewall upgrade. 2019-06-23 13:38:52