Skip to main content

Unplanned Outage: Server Farm switch upgrade failed

Last Updated:
2010-10-01 04:00:00
Event:
2010-10-01 04:00:00
Status:
Closed
Brief Description:
User Impact:
N/A
Workaround:
There is no workaround for this issue
Current Status:
N/A
Services Affected:
Full Description:
The upgrade of the server farm switches failed this morning and backed out. We lost intradatacenter communication, lost communication with all servers in the server farm from approx 05:20 until 05:30.
CIT TDX ID:



Timeline of Changes

Description Current Status Date Time
Server farm connectivity has been restored. CIT Personnel are working to assess and correct any remaining issues.\n Server farm connectivity has been restored. CIT Personnel are working to assess and correct any remaining issues.\n 2010-10-01 04:00:00
At this time all affected service are available.\n At this time all affected service are available.\n 2010-10-01 04:00:00