Unplanned Outage: Server Farm switch upgrade failed
Last Updated:
2010-10-01 04:00:00
Event:
2010-10-01 04:00:00
Status:
Closed
Brief Description:
User Impact:
N/A
Workaround:
There is no workaround for this issue
Current Status:
N/A
Services Affected:
Full Description:
The upgrade of the server farm switches failed this morning and backed out. We lost intradatacenter communication, lost communication with all servers in the server farm from approx 05:20 until 05:30.
CIT TDX ID:
Timeline of Changes
Description | Current Status | Date | Time |
---|---|---|---|
Server farm connectivity has been restored. CIT Personnel are working to assess and correct any remaining issues.\n | Server farm connectivity has been restored. CIT Personnel are working to assess and correct any remaining issues.\n | 2010-10-01 | 04:00:00 |
At this time all affected service are available.\n | At this time all affected service are available.\n | 2010-10-01 | 04:00:00 |