Unplanned Outage: FIM Synchronization Service

Last Updated:
2013-01-15 05:00:00
Event:
2013-01-15 05:00:00
Status:
Closed
Brief Description:
Changes to mail routing, EGA changes, reference group changes, etc.
User Impact:
N/A
Workaround:
There is no workaround for this issue
Current Status:
N/A
Services Affected:
Full Description:
The Microsoft Task Scheduler on the FIM server hung between 2 AM and 3 AM on 1/15. As a result, no FIM services ran until the machine was rebooted. The reboot was at 11:11 AM and the noon update cycle ran as scheduled and completed at 12:09 PM.\n\nChanges to mail routing, EGA changes, reference group changes, etc. made after 2 AM 1/15 were not reflected in Active Directory until 12:09 PM 1/15. Most users would not notice; those who changed mailrouting or an EGA during this period experienced a delay before the changes took effect.
CIT TDX ID:



Timeline of Changes

Description Current Status Date Time
The noon update cycle ran as scheduled and completed at 12:09 PM. The noon update cycle ran as scheduled and completed at 12:09 PM. 2013-01-15 05:00:00