Skip to main content

Unplanned Outage: Power Restored at CCC

Last Updated:
2009-07-08 04:00:00
Event:
2009-07-07 04:00:00
Status:
Closed
Brief Description:
Physical Infrastructure
User Impact:
N/A
Workaround:
There is no workaround for this issue
Current Status:
N/A
Services Affected:
Full Description:
Power has been restored to CCC. The campus services that were affected by this outage are operational again.
CIT TDX ID:



Timeline of Changes

Description Current Status Date Time
The cause of the July 7 power outage at CCC: Due to a malfunction of a UPS, the electrical feed to half of the CCC machine room was lost. The cause of the July 7 power outage at CCC: Due to a malfunction of a UPS, the electrical feed to half of the CCC machine room was lost. 2009-07-08 04:00:00
Power outage at CCC ETA to a resolution is unknown. Power outage at CCC ETA to a resolution is unknown. 2009-07-07 04:00:00
Some Central IT services are affected. Some Central IT services are affected. 2009-07-07 04:00:00
Permit Server is down. Permit Server is down. 2009-07-07 04:00:00
The CCC UPS has been brought back up. The Permit server is now available once again.\nCIT Support Staff are currently trying to revive affected systems at CCC. The CCC UPS has been brought back up. The Permit server is now available once again.\nCIT Support Staff are currently trying to revive affected systems at CCC. 2009-07-07 04:00:00
Power has been restored to CCC; a small number of services are still down. CIT is working on these.\n Power has been restored to CCC; a small number of services are still down. CIT is working on these.\n 2009-07-07 04:00:00
RedRover-Secure is one of the services that is still down. RedRover-Secure is one of the services that is still down. 2009-07-07 04:00:00
Campus services have been restored, including RedRover-Secure. \n\nCIT and Cornell electricians are continuing to work with the UPS vendor to identify and correct an issue with the UPS. It is not anticipated that this work will cause additional outages. Campus services have been restored, including RedRover-Secure. \n\nCIT and Cornell electricians are continuing to work with the UPS vendor to identify and correct an issue with the UPS. It is not anticipated that this work will cause additional outages. 2009-07-07 04:00:00