Performance: SAN Volume Controller

Last Updated:
2012-02-06 05:00:00
Event:
2012-02-05 05:00:00
Status:
Closed
Brief Description:
User Impact:
N/A
Workaround:
There is no workaround for this issue
Current Status:
N/A
Services Affected:
Full Description:
A redundant pair of SAN Volume Controller nodes (SVC nodes) provide "storage virtualization" capabilities to the Storage Farm service. These SVCs are in the data path between storage arrays and servers. The first SVC node was upgraded successfully. The upgrade for the second (of two) nodes did not complete normally, for unknown reasons. The storage service is still running, but without redundancy, until the second node can be upgraded. It is possible that some services may see a performance impact.
CIT TDX ID:



Timeline of Changes

Description Current Status Date Time
Technical Support staff are reporting an ETA for full redundancy to be restored at 2:00 AM\n Technical Support staff are reporting an ETA for full redundancy to be restored at 2:00 AM\n 2012-02-06 05:00:00
Technical Support staff are reporting an ETA for full redundancy to be restored at 4:00 AM Technical Support staff are reporting an ETA for full redundancy to be restored at 4:00 AM 2012-02-06 05:00:00
Technical Support staff are reporting an ETA for full redundancy to be restored at 12:00 pm. Technical Support staff are reporting an ETA for full redundancy to be restored at 12:00 pm. 2012-02-06 05:00:00
IBM Field Services will be preparing & installing a new SVC node this morning working with Cornell Technical Support staff. The new node will replace the single node which did not upgrade normally.\n\nWe are expecting an ETA for full redundancy to be restored at noon. \n IBM Field Services will be preparing & installing a new SVC node this morning working with Cornell Technical Support staff. The new node will replace the single node which did not upgrade normally.\n\nWe are expecting an ETA for full redundancy to be restored at noon. \n 2012-02-06 05:00:00
Preparations are taking longer than expected an ETA for full redundancy should now be restored by 5:00PM. There have been no reports of problems associated with this issue. Preparations are taking longer than expected an ETA for full redundancy should now be restored by 5:00PM. There have been no reports of problems associated with this issue. 2012-02-06 05:00:00
As of 5:15 PM, this problem has been resolved. As of 5:15 PM, this problem has been resolved. 2012-02-06 05:00:00
CIT is currently working with the storage vendor to complete this upgrade now. There is currently no ETA for the completion of the upgrade of the second SVC node. Updates will be provided. CIT is currently working with the storage vendor to complete this upgrade now. There is currently no ETA for the completion of the upgrade of the second SVC node. Updates will be provided. 2012-02-05 05:00:00
Current ETA for full redundancy to be restored is 8:30 PM. Current ETA for full redundancy to be restored is 8:30 PM. 2012-02-05 05:00:00
Technical Support staff are reporting an ETA for full redundancy to be restored at 10:00 PM Technical Support staff are reporting an ETA for full redundancy to be restored at 10:00 PM 2012-02-05 05:00:00
Technical Support staff are reporting an ETA for full redundancy to be restored at 12:00 AM\n Technical Support staff are reporting an ETA for full redundancy to be restored at 12:00 AM\n 2012-02-05 05:00:00